Black Lab 'B' - Weekly Update
Overview:
Accomplished This Week
Table Progress:- Beta version of the game released to certain members of the public, including the laboratory and various Experts, as defined in the familiarization presentations
- Tested the Beta version of the game and received various error reports which focus on Content, Game-Play, and general Game Design theory
- Project Management Committee distributed the work load for the Open House amongst members of the laboratory
To Be Accomplished Next Week
- Progress to be made in Final Reports
- Meeting on Tuesday to confirm all aspects of Open House (Poster, Design Manual, etc) are completed
- Testing of the Game concluded, all concerns fixed within the game
- Beta to be re-released as full game
- Open House presentations
David's Group
Table: B6
Topic: Lessons 24-27
Accomplished This Week
Topic: Lessons 24-27
Accomplished This Week
David released Beta version of the game to the laboratory and selective Experts, as identified during the Familiarization presentation, for testing
Received testing results from the laboratory
Fixed content material bugs and errors
- Begin work on the Final Report
- Prepare for Open House Presentation
- Fix any remaining issues with the game
Gavin's Group
Table:B5
Topic: Lessons 20-23
Accomplished This Week
To Be Accomplished Next Week
- The team tested game looking for errors in assigned levels. any errors found were reported to david so he could fix them
- David fixed them
- Started design manual
- Divided labour for design manual and final report
To Be Accomplished Next Week
- Finish design manual
- Finish final report
- Finish 253...yay!
Stephen's Group
Table: B1Topic: Lessons 1-5
To Be Accomplished Next Week
Christine's Group
Accomplished This Week
- Help files were completed and submitted
- Game Testing, documented all bugs and errors on a Google Doc
- Sent error report to David
To Be Accomplished Next Week
- Completion of Final Report
- Jason at open house
Christine's Group
Table: B-2
Topic: Lessons 6-10
Accomplished This Week
To Be Accomplished Next Week
Accomplished This Week
- The team tested their part of the game and pointed out the errors to be corrected by David
- The team gave a list of image sources that were used in the game for references
- Divide the work for the final report
- Finish the poster for the Open House
- Work on the Final Report that will be due on April 19th 2010
Brandon's Group
Table: B-3
Topic: Lessons 11-15
Accomplished This Week
- 1st version of game was finished and testing was done
- Issues found in testing reported to David
- Jimin, Chris, Curtis: Start final report
- Brandon: prep for final presentation
Jesse's Group
Table: B-4
Topic: Lessons 16-19
Accomplished This Week
- Sent finalized pictures and questions to David
- 1st version of game completed
- Tested it and reported any errors or glitches to David
- Retested the game in the short lab and reported any other errors (missed or new) to David
- Began working on Final Report
To Be Accomplished Next Week
- Completion of Final Report